Our refined plan will reduce the farm's energy producing capacity to 5MW, down from 9MW.

Formal comments and objections to RN's planning application to the Victorian Planning Minister closed in late September.

Three factors have influenced RN's decision to refine its plan.

  • Response from our community (two objections and one comment)
  • Response from referral authorities including the CFA.
  • Feedback from the energy industry around current connection issues which indicates that for our ambitions (to supply Newstead or at least all of the 3462 postcode with renewable energy) 5MW is the optimal size.

View the submitted amended plan for a 5MW solar farm here from 26 October 2020.

More News & Project Updates

Construction to begin!

Construction is set to begin on our solar farm in Newstead. Jointly launched today by the Victorian Minister for Energy, Environment and Climate Action, The Hon. Lily D’Ambrosio, MP and Member for Bendigo West, The Hon. Maree Edwards, with Flow Power, the Renewable Newstead team and local Dja Dja Wurrung representatives.

Read More

Community Visioning

Flow Power is kicking in to help fund Newstead’s community visioning day on September 10. Flow Power will build, own and operate our solar farm and retail the electricity to customers.

Read More